Back to search
SAM.govRef 36C25627Q0085

J061--586-Switchgear and ATS Investigation and Repair Service (VA-27-00015294)

VVETERANS AFFAIRS, DEPARTMENT OF logo
Contracting officeDepartment of Veterans Affairs
ActiveServicesNAICS 811310
Submission deadlineNov 18, 202605:00 PM EST3 days left
PublishedNov 13, 2026
LocationRIDGELAND, MS
Notice type
Combined Synopsis/Solicitation
Product or service code
J061 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRIC WIRE AND POWER DISTRIBUTION EQUIPMENT
Set-aside
Not specified
Place of performance
RIDGELAND, MS
Official notice
View on SAM.gov ↗

Description

Q1: Under page 6 para 4.4, the SOW requires: "Generator/AS Integration Testing (as needed)..." What are the Makes, Models, S/Ns, and years of manufacture of the CAT generators (or other generators, that connect to these ATSs or associated equipment), so we can conduct the load banking as requested?" The CAT gens are 650 kw and 2250 kw. Load banking would only be needed if during the process it is needed for investigative purposes or to prove out repairs.

Q2: "Does the government want CAT to accomplish or aid in the accomplishment of task 1 under para 4.4 "Remove/reconnect bias signals during generator tuning (if required)?" The use of CAT to carry out any tasks would be at the vendors discretion.

Q3: "Does the government want CAT to accomplish or aid in the accomplishment of task 2 under para 4.4 "Remove/reconnect bias signals during generator tuning (if required)?" The use of CAT to carry out any tasks would be at the vendors discretion.

Q4: If we are an authorized CAT generator service company, can we complete the tasks under para 4.4 without bringing in CAT? Yes Q5: The SOW states, "The solicitation requests, "Recommendations for future reliability improvement." (page 6, para 4.5)," and the main task is "repair services for facility switchgear and ATS systems that are malfunctioning." What will the government allow under this solicitation if the work required to accomplish the main task is outside the scope of the SOW. That is, will the government modify an award if more substantial repairs are required?  Under this contract, the government is looking for the vendor to establish what the issues with the system are and to repair those issues to have a fully operational system. The recommendations for improvement if directly associated to bring the system back to operational status would be considered part of repairs. Any recommendations that would assist in the future that are not required at this time to make the system functional would be submitted to the government for future contractual consideration. What are the total quantities and types of breakers, and what are their amperage ratings and trip-unit manufacturers/models? The purpose of the site visit was for the vendor to get the information required. GE/ABB/ASCO. Contract is investigative/repair and vendor will acquire information during performance. What breaker testing methods are expected, including whether primary- or secondary-injection testing is required? No expectations. Testing will be accomplished IAW NFPA 70 B and E. What are the quantities and types/models of protective relays requiring inspection or testing? The purpose of the site visit was for the vendor to get the information required. Contract is investigative/repair and vendor will acquire information during performance. What types and quantities of switches are included in the scope? The purpose of the site visit was for the vendor to get the information required. Contract is investigative/repair and vendor will acquire information during performance. Is any gear located on mezzanines? Is there suitable access and space near the electrical rooms to stage a generator and test equipment? No equipment is on mezzanine. Room is available. Are equipment photos or an equipment schedule available? The purpose of the site visit was for the vendor to get the information required. Contract is investigative/repair and vendor will acquire information during performance. What are the total quantities and types of breakers, and what are their amperage ratings and trip-unit manufacturers/models? The purpose of the site visit was for the vendor to get the information required. GE/ABB/ASCO. Contract is investigative/repair and vendor will acquire information during performance. What breaker testing methods are expected, including whether primary- or secondary-injection testing is required? No expectations. Testing will be accomplished IAW NFPA 70 B and E. What are the quantities and types/models of protective relays requiring inspection or testing? The purpose of the site visit was for the vendor to get the information required. Contract is investigative/repair and vendor will acquire information during performance. What types and quantities of switches are included in the scope? The purpose of the site visit was for the vendor to get the information required. Contract is investigative/repair and vendor will acquire information during performance. Is any gear located on mezzanines? Is there suitable access and space near the electrical rooms to stage a generator and test equipment? No equipment is on mezzanine. Room is available. Are equipment photos or an equipment schedule available? The purpose of the site visit was for the vendor to get the information required. Contract is investigative/repair and vendor will acquire information during performance.

The rest of this notice

The buyer's named contact and the award details for this notice are free. Create an account to open the full record.

  • Contact the buyer directly
  • See who won, and for how much
  • Get alerts for opportunities like this one
Create a free account

Free — no card, no trial clock.

Get new Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance contracts by email — free, no card needed.
Create a free alert